Amazon Warrington

Completed

Start Date

December 2016

Client

ISG

Duration

39 weeks

Overview

Multi-national company Amazon commissioned the construction of a new £50 million fulfilment centre in 2016 which created 1,200 new full time jobs on the Omega South complex in Warrington.

This location, along with Amazon’s Tilbury location which we’re also currently doing works on, facilitated the introduction of Amazon Robotics to try and improve their service for customers.

What did we do?

For this project, we were appointed to do the mezzanine floor foundations, breakout the ground floor slab, construct the external substructures and retaining walls and install service trenches and ducting.

We also put in internal and external drainage, road formation and tarmac, as well as attendance to ground stabilisation and soft landscaping.