Contract Meeting No. 8 – 24.04.2018

On the 24.04.2018, we had our eighth contract meeting with our client regarding any updates with the work.

As at 22.04.2018, we are currently at:

  • Zero accidents or near misses.
  • 20,721 man hours works.
  • Fencing has been erected on Cab Road, entrance solely being used for Network Rail Employees.
  • Monitoring vibration and noise levels near adjacent buildings.
  • Removal of glazed bricks to commence.
  • Site kept secure 24/7.