Scope
The Scope of Works is broken down into the following sections: –
Asbestos Removal
A specialist Asbestos removal company will be employed to safely remove all Asbestos from site prior to works proceeding.
Archaeology
Archaeologists have been employed to undertake Archaeological and heritage survey of the site. This involves investigating the ground for Archaeological remains.
Bulk Excavation
Murraywood will then knock down any existing walls that have been discovered ready for the Bulk Excavation. Murraywood will then do a Bulk Excavation to a given level. Ready for Piling Matt construction.
Forming Piling Matt
During the back-filling for the Piling Matt the ash material that has been stored on site will be use first followed by 6F2 until the correct height is achieved.
Site Strip
All tarmac and cobbles will be removed from site. This will leave a layer of ash which the cobbles had been laid on. The ash will be reduced to natural ground, storing on site until a later date. During this process Asbestos was found in the ground so a specialist company will come in and remove it.